El Salvador |
1997 |
"El Ronco" Power Plant |
18.6 MW Thermal Power Plant |
Ferrostaal - MAN, Alemania |
Mechanical
|
El Salvador |
1997 |
Outside Plant |
Outside Plant - Telephony |
AT&T, USA |
Telefonia
|
El Salvador |
1996 |
Nejapa Power Plant Extension |
53 MW Thermal Power Plant |
Wartsila Diesel, Finlandia |
Electrical, Mechanical, Civil
|
El Salvador |
1995 |
Nejapa Power Plant |
91 MW Thermal Power Plant |
Black & Veatch, USA / Wartsila, Finlandia |
Electrical, Mechanical, Civil
|
El Salvador |
1996 |
Outside Plant |
Outside Plant - Telephony |
ERICSSON, Suecia |
Telefonia
|
El Salvador |
1992 |
Distribution Lines. |
Electrical Distribution Power Lines. |
Privados, El Salvador |
Electrical
|
El Salvador |
1992 |
Distribution Lines for CEL |
Electrical Distribution Power Lines. |
CEL, El Salvador |
Electrical
|
Guatemala |
2008 |
Modification of the feed system to the crusher in mina Marlin. |
mechanical Installation |
M3 Engineering & Technology Corp., USA |
Mechanical
|
Guatemala |
2006 |
Combined Cycle Arizona |
Construction of the civil and electromechanical works, supply of materials. |
Duke Energy, USA |
Mechanical
|
Guatemala |
2006 |
Maintenance works of Klin #3 in "Planta San Miguel". |
Unassemble, reparation and erection of load seals and unloding of klin #3. Unassemble, fabrication and erection of exhaust duct o cooling filter. |
Cementos Progreso |
Mechanical
|